Every residential project in Karnataka with more than eight units or more than 500 square metres of land must be registered with the Karnataka Real Estate Regulatory Authority (K-RERA). The RERA project page is a public document that shows approvals, timelines, floor plans, and the builder’s legally declared promises. Knowing how to read this page helps you verify what the sales team tells you and spot warnings before you book.
Where to Find Karnataka RERA Project Details
Go to rera.karnataka.gov.in and click on “Registered Projects”. You can search by project name, builder name, RERA registration number, or location. Each project has a unique registration number that begins with PRM/KA/RERA, and this number must appear on all the builder’s marketing material and agreements. If the builder says the project is RERA-registered but you cannot find it on the website, that is a red flag. Do not book until you have seen the live RERA page yourself.
What Each Section on the RERA Page Means
The Project Details section shows the promoter’s name, the total land area, the number of blocks and units, and the type of land (freehold or leasehold). Cross-check the promoter’s name with the sale agreement draft—if they do not match, ask why. The Project Status field will say either Ongoing or Completed; if it says Completed but the builder is still marketing new inventory, verify whether those units are part of a later phase under a separate RERA number.
The Completion Date is the builder’s legal commitment. This is not a target or an estimate; if the project is not finished by this date, buyers are entitled to compensation under RERA. Check this date against what the sales brochure promises. The Approvals tab lists the sanctioned plan number, occupancy certificate (if issued), and commencement certificate. A project without a commencement certificate should not have started construction, and one without an occupancy certificate cannot legally hand over flats. If the builder is asking you to take possession, the OC must already be issued and uploaded on the RERA page.
The Layout Plan section contains the sanctioned site plan and floor plans. Download these PDFs and compare them with what the builder’s brochure shows. Discrepancies in the number of towers, unit sizes, or common amenities mean either the brochure is outdated or the builder is marketing something not yet approved. The Project Proforma declares the carpet area, built-up area, and loading factor for each unit type. If the sales team quotes a different carpet area from what the RERA page shows, insist on the RERA figure in your agreement—it is the legally binding one.
Red Flags When You Check Karnataka RERA Project Details
If the RERA registration is about to expire and the project is not yet complete, check whether the builder has applied for an extension. A lapsed registration means the project is non-compliant, and buyers lose the protection RERA offers. If the completion date has already passed but construction is still ongoing, the builder owes compensation—ask how much and when it will be paid, and get it in writing. Some builders file extensions or revised completion dates just before the deadline; if you see multiple extensions on the update history, it signals repeated delays.
Another warning is when the RERA page shows a different phase or block count from what is being sold. Builders sometimes register only part of a larger layout and launch other blocks without separate RERA numbers, which is illegal. If the unit you are interested in is not explicitly listed in the RERA inventory, do not proceed. Also check the quarterly progress reports under the “Project Updates” tab—if reports are missing or show little construction progress months before the declared completion date, the timeline is unrealistic.
BLR Realty checks the RERA page of every project we recommend and compares it line by line with the builder’s marketing claims. We also cross-check it against the sanctioned plan documents. If something does not match, we either get it clarified in writing or we do not recommend the project.
BLR Realty charges buyers zero brokerage and checks every project before recommending it. For a free shortlist of verified homes that fit your budget and preferred area, WhatsApp us on +91 63617 88167.
Frequently Asked Questions
What is the RERA completion date and how is it different from possession date?
The RERA completion date is the legally binding deadline by which the builder must finish construction and obtain the occupancy certificate. The possession date in your agreement may be the same or slightly later, but if the RERA completion date passes without the project being finished, the builder must pay compensation for the delay even if your individual possession is not yet due.
What happens if the project is delayed past the RERA completion date?
If the builder does not complete the project by the declared completion date, you are entitled to interest for every month of delay at the rate prescribed under the Karnataka RERA rules, or a refund of your payments with interest if you choose to withdraw from the project. You can claim this through a complaint on the RERA website, and the builder must either pay or explain why the delay was beyond their control with acceptable proof.
How do I check if a Karnataka RERA project registration is still valid?
On the RERA project page, look for the registration validity date in the Project Details section. If that date has passed and the project status is still Ongoing, check the Updates tab to see if an extension was filed and approved. A project operating with an expired RERA registration loses its legal standing, and buyers in such projects face difficulty claiming their rights.
Can a builder change the floor plan or unit size after RERA registration?
No, any change to the sanctioned layout, unit carpet area, or common facilities requires the builder to file a revised plan with both the local planning authority and RERA, and obtain approval before making the change. If your builder shows you a layout that differs from the RERA page, ask to see the approved revision on the RERA site before you book.